Finishing stages, in order
Every stage has its place, and doing one too early or too late is paid for in demolition and rework.
Why the order matters
Finishing is not a list of items done in any order. Each stage is built on the one before it and covers it: tiling covers waterproofing and plumbing, gypsum covers electrical conduits and air-conditioning copper, and paint covers plaster. Any mistake in one stage hides under the next, and fixing it later means demolishing everything on top of it.
The right order does two things: it protects finished work from the work that follows, and it gives you the chance to check each stage while it is still exposed. For example, if air-conditioning copper is run after tiling, you will usually find broken tiles to let a pipe through, and if all the paint is finished before installations, every mark is fixed with a visible patch.
Design itself is a stage, not a luxury: the position of every socket, water outlet and lighting point is set by the position of the furniture, the kitchen and the dressing room. If first fix is done before design, you will usually find the socket behind the wardrobe and the light not above the dining table, and moving them afterwards means chasing walls and relocating points.
The stages in order
- Handover of the unit, inspection and actual measurements.
- Design and approved drawings, with electrical and lighting points.
- Demolition and modifications: new walls or moving a kitchen or bathroom.
- Electrical and plumbing first fix.
- Air-conditioning copper piping, condensate drainage and power.
- Plaster corrections and filling the chases.
- Waterproofing, flood test and pressure test.
- Gypsum board and suspended ceilings.
- Ceramic and porcelain: walls first, then floors.
- Skim coat and the first coats of paint.
- Carpentry and door installation.
- Sanitary ware, switches, sockets and lighting.
- Kitchen and dressing room installation.
- The final coat of paint, cleaning and handover.
Testing before any tiling
Waterproofing in bathrooms, the kitchen and terraces is applied to the floor and turned up the walls to a suitable height, and detailed around drainage pipes, floor drains and corners. Ask about the type of waterproofing and make sure it is written in the quotation.
After waterproofing comes a flood test: the area is filled with water and left long enough, and the ceiling of the floor below and the adjoining walls are checked for seepage. The pressure test on water pipes and air-conditioning copper is done while they are still exposed.
If tiles are laid before both tests and a leak appears, there is usually no solution other than removing the tiles and the waterproofing and redoing them, and if the water reaches the neighbours the problem grows. That is why this is one of the most important points to check yourself.
In villas and top floors, roof waterproofing has its own stage, and it is best applied and tested before any interior finishing on the floor below, because any seepage after gypsum and paint means stains, peeling and redoing work that was complete.
What to check at each stage
- First fix: the number and positions of points match the drawing, a distribution board with separate circuits for air conditioners and the kitchen, good drainage falls, and a condensate drain near every air conditioner. Photograph every wall before it is closed, with measurements from the floor and the nearest corner.
- Gypsum: make sure everything above the ceiling is finished and checked, the metal frame is properly hung before the boards, and that there are access panels at air-conditioning units and valves.
- Tiling: level checked with a spirit level, regular joints, falls towards the drain, and no tile that sounds hollow when tapped.
- Kitchen and dressing room: make sure they were measured on site after tiling and plaster, not from the drawing alone, because the tile thickness alone can stop the units fitting their place.
Final handover
Before handover, walk the unit room by room and write a snag list: a scratch, a door that rubs, a socket that does not work, a missing joint. Every item with its location and photo.
Test everything yourself: open every tap and watch the drainage, switch on every circuit and the air conditioners, and close every door and cabinet.
And ask for the as-built drawings and photos of first fix before it was closed, because you will usually need them if you ever drill into a wall later.
And final cleaning is more than sweeping: make sure cement and paint residue is removed from tiles, glass and aluminium, and that floor drains and drainage are cleared of any debris that fell in during the works.
Stage questions
What people ask about the order of finishing.
What is the correct order of apartment finishing stages?
Handover, design and demolition, then first fix, plaster, waterproofing and tests, then gypsum and tiling, then paint, carpentry and installations, and finally the last coat and handover.
Can tiles be laid before the gypsum?
Yes, if the floor is covered with real protection, but it is usually safer to finish the gypsum first so scaffolding and chasing do not affect laid flooring.
Is paint done before or after the kitchen?
Most coats of paint go before the kitchen and dressing room, and the final coat after installation to cover any marks.
When are the pressure test and flood test done?
The pressure test after first fix and before the pipes are closed, and the flood test after waterproofing and before tiling.
How do I start with Zavora?
Send on WhatsApp the area, the size and the state of the unit. An engineer books a site visit, then you receive a written itemised quotation.
More guides
Finishing guidesWant your finishing done in the right order?
Send your unit details on WhatsApp, an engineer inspects the unit, then you receive a written itemised quotation.